When backup power fails in a hospital, every second counts. This week, our team completed a rapid control panel upgrade on one of the generators supporting a major London hospital.

After surveying the issue, we designed and installed a new main control panel, rewired the engine loom, and commissioned a DeepSea 7420 controller, providing advanced and reliable control of the entire system.

Once installed, we ran full function and load tests, logging and analysing all alternator outputs before signing off. The new system is now fully operational and ready to take critical load at a moment’s notice.

From fault to fix, we delivered the full solution in under one week. A clear example of how Barbour responds to critical power challenges quickly and without compromise.

Need support with your backup power? Chat to our team today.

More resources

  • The Challenges of Installing Infrastructure in City Centre Buildings

    Read more →

  • 5 Early Warning Signs of Electrical Infrastructure Failure

    Read more →

  • 5 Benefits of Preventive Maintenance for Electrical Infrastructure

    Read more →

  • What Actually Happens During a Generator Load Bank Test?

    Read more →

Get a personal consultation